September 4, 2023· Finalize Topic and Methodology
· Conduct initial research
October 1, 2023· Deliverable 1: Detailed Project Plan
· Deliverable 1: Project Webpage
October 18 –  November 27, 2023· Design Front-end Layout (Web page for Ticket Purchaser and Event Organizer)
· Smart Contract Development
· Literature Review
November 28 – January 15, 2023· Integration of Blockchain and Platform Back-end
· Front-end Implementation (Webpage)
December 28, 2023· Integration of Blockchain and Platform Back-end
· Front-end Implementation (Webpage)
January 8 – January 12, 2024· First Presentation
January 21, 2024· Deliverable 2: Preliminary Implementation
· Deliverable 2: Detailed Interim Report
February 30, 2024· Front-end Implementation (Mobile App)
· Build Relevant Test Cases for Trials
March 15, 2024· Final Review and Improvement
· Implementation to the Live Market for the Final Result
March 30, 2024· Preparation of the Project Poster
· Preparation of the Final Presentation
· Final Review of the Project
April 15 – April 19, 2024· Final Presentation
April 23, 2024· Deliverable 3: Final report
· Deliverable 3: Finalized Tested Implementation
April 26, 2024· Project Exhibition