Progress

TimelineTask & MilestoneProgress
1 OctDeliverables of Phase 1
– Detailed Project Plan
– Project Webpage
🟢
Oct – NovSystem Design
– Prepare required data
– Data Structure
– Main UI Design
🟢
Nov – Jan 2024Implementation
– Back-end
🟢
8-12 Jan 2024First Presentation🟢
21 Jan 2024Deliverables of Phase 2
– Preliminary implementation
– Detailed interim report
🟢
Jan 2024 – Feb 2024UI Design
– Further UI Design
– Improve the previous UI
🟢
Feb 2024 – Apr 2024Implementation
– Front-end
🟢
23 Apr 2024Deliverables of Phase 3
– Finalized tested implementation
– Final report
🔴
26 Apr 2024Project exhibition🔴